Tuesday, November 20, 2012

Los Angeles Airport (LAX) New Tom Bradley International Terminal (TBIT) Project

Latest photo update on the LAX New TBIT project. The first gate is already operational with the rest of the terminal being brought online in phases. You can see the Cathay Pacific aircraft at the operational gate.  This project is one of the projects in the larger LAX Modernization Program.

New Tom Bradley International Terminal Project
- part of the LAX Modernization Program (over US$4 billion)
- US$1.5 billion
- 18 new gates (9 for the A380)
- Upgraded customs and immigration federal inspection areas
- Capacity – 4,000 pax per hour, up from current 2,800 pax per hour
- Great Hall with 150,000 sqft (14,000m2)for premier dining and retail shopping
- Architect – Fentress and Associates
- Completion of Phase 1 West Side Gates and Great Hall – Spring 2013
- Completion of Phase 2 East Gates – end 2013

LAX Project Fact Sheets (click here)

Source of information and pictures: LAX website