Tuesday, December 24, 2013

Brisbane Airport (BNE) Main Runway Resurfacing


Map of Main Runway Resurfacing

Brisbane Airport Main Runway Resurfacing
- Cost A$15m, completed Sep 2012
- replaced the 11 year old asphalt in the touchdown zones in the touchdown zones at either end of the runway
- more than 200,000 work hours and 18,000 tonnes of asphalt
- 6 months of night work, resurfacing work conducted between midnight and 5am up to six nights a week.
- up to 100 personnel and 60 items of plant and equipment per shift

Click here for more information.

Click here to see a 3 min video of the project.  It shows a time lapse video of the resurfacing work.

Source: Brisbane Airport website

Time Lapse video of the resurfacing


Saturday, December 21, 2013

Passenger Teminal at Al-Maktoum International Airport, Dubai (DWC)

The Passenger Terminal at Al-Maktoum Airport opened on 27 Oct 13 for commercial passenger service.  The initial capacity of the terminal is 5 million passengers per annum.

Passenger Terminal Map (1st phase)


Source: Dubai Airports website

ACRP Report 96 - Apron Planning and Design Handbook




ACRP has released a report on Aircraft Apron planning and design.  The key chapters are:
- Apron Planning and design Process
- understanding the Apron Environment
- Apron Planning and design

I have extracted some diagrams from the handbook that I thought were interesting.

Source: ACRP Report 96

Jet Blast Contours