Tuesday, December 24, 2013

Brisbane Airport (BNE) Main Runway Resurfacing


Map of Main Runway Resurfacing

Brisbane Airport Main Runway Resurfacing
- Cost A$15m, completed Sep 2012
- replaced the 11 year old asphalt in the touchdown zones in the touchdown zones at either end of the runway
- more than 200,000 work hours and 18,000 tonnes of asphalt
- 6 months of night work, resurfacing work conducted between midnight and 5am up to six nights a week.
- up to 100 personnel and 60 items of plant and equipment per shift

Click here for more information.

Click here to see a 3 min video of the project.  It shows a time lapse video of the resurfacing work.

Source: Brisbane Airport website

Time Lapse video of the resurfacing


No comments:

Post a Comment

Related Posts Plugin for WordPress, Blogger...